Unlock AI power-ups β upgrade and save 20%!
Use code STUBE20OFF during your first month after signup. Upgrade now β
By edureka!
Published Loading...
N/A views
N/A likes
Get instant insights and key takeaways from this YouTube video by edureka!.
Project Cost Management Fundamentals
π Project cost encompasses all resource expenses, including human resources (salaries, CTC, per diem), travel (airfare, visa, lodging), materials (software), and training, all leading to incurred costs.
β οΈ Cost estimation is challenging due to numerous influencing factors outside direct project control, such as delays and change requests from the customer, which can lead to cost escalation.
π The Cost Management Plan outlines procedures for planning, structuring, and controlling project costs, defining parameters like unit of measure, level of precision, and acceptable accuracy range (e.g., ).
Cost Estimation Techniques and Financial Concepts
π’ Three levels of estimation accuracy exist: Rough Order of Magnitude (ROM) with to variance, Budget Estimate ( to ), and Definitive Estimate ( to ).
β‘οΈ Analogous estimation uses analogies from past similar projects, while Parametric estimation applies historical rates (e.g., \X$ per cubic meter) and may adjust for inflation.
π Direct costs are tied specifically to the project (e.g., site travel, resource billing), while indirect costs are shared organizational overheads like electricity, security, and supporting management staff.
πΈ Sunk costs represent money already spent; the dictum is "Don't cry over spilled milk"βit might be better to close a non-viable project rather than investing further.
Budget Determination and Reserve Analysis
π΅ The Cost Baseline is established by aggregating activity cost estimates (often via Bottom-Up estimation) and adding the Contingency Reserve for known unknowns (identified risks).
π° The Project Budget equals the Cost Baseline plus the Management Reserve, which covers unknown unknowns and is controlled by senior management, not the Project Manager.
π Funding Limit Reconciliation involves aligning the project's planned fund outflow (resource needs, vendor payments) with the organization's internal funding constraints and cash flow limitations.
Cost Control and Monitoring
π Cost control involves monitoring the status against the Cost Baseline and managing changes efficiently, utilizing techniques like Earned Value Management (EVM) and forecasting.
π The Cost Baseline is the authorized budget against which project cost performance is monitored, contrasting Actual Cost (AC) with planned spending.
Key Points & Insights
β‘οΈ Project costs are internally funded by the organization; the customer payment (contract value) is a separate commercial discussion and does not alter the internal Project Cost or Budget.
β‘οΈ Contingency Reserve is for known risks and is part of the Project Manager's Cost Baseline; Management Reserve is for unknown risks and is outside the PM's direct purview.
β‘οΈ When determining costs, consider market conditions like Sole Source (single vendor, higher fee) versus Oligopoly (many vendors, higher negotiation control) for procuring specialized services.
πΈ Video summarized with SummaryTube.com on Nov 14, 2025, 19:51 UTC
Find relevant products on Amazon related to this video
As an Amazon Associate, we earn from qualifying purchases
Full video URL: youtube.com/watch?v=_5Pz3lid4aA
Duration: 58:12
Get instant insights and key takeaways from this YouTube video by edureka!.
Project Cost Management Fundamentals
π Project cost encompasses all resource expenses, including human resources (salaries, CTC, per diem), travel (airfare, visa, lodging), materials (software), and training, all leading to incurred costs.
β οΈ Cost estimation is challenging due to numerous influencing factors outside direct project control, such as delays and change requests from the customer, which can lead to cost escalation.
π The Cost Management Plan outlines procedures for planning, structuring, and controlling project costs, defining parameters like unit of measure, level of precision, and acceptable accuracy range (e.g., ).
Cost Estimation Techniques and Financial Concepts
π’ Three levels of estimation accuracy exist: Rough Order of Magnitude (ROM) with to variance, Budget Estimate ( to ), and Definitive Estimate ( to ).
β‘οΈ Analogous estimation uses analogies from past similar projects, while Parametric estimation applies historical rates (e.g., \X$ per cubic meter) and may adjust for inflation.
π Direct costs are tied specifically to the project (e.g., site travel, resource billing), while indirect costs are shared organizational overheads like electricity, security, and supporting management staff.
πΈ Sunk costs represent money already spent; the dictum is "Don't cry over spilled milk"βit might be better to close a non-viable project rather than investing further.
Budget Determination and Reserve Analysis
π΅ The Cost Baseline is established by aggregating activity cost estimates (often via Bottom-Up estimation) and adding the Contingency Reserve for known unknowns (identified risks).
π° The Project Budget equals the Cost Baseline plus the Management Reserve, which covers unknown unknowns and is controlled by senior management, not the Project Manager.
π Funding Limit Reconciliation involves aligning the project's planned fund outflow (resource needs, vendor payments) with the organization's internal funding constraints and cash flow limitations.
Cost Control and Monitoring
π Cost control involves monitoring the status against the Cost Baseline and managing changes efficiently, utilizing techniques like Earned Value Management (EVM) and forecasting.
π The Cost Baseline is the authorized budget against which project cost performance is monitored, contrasting Actual Cost (AC) with planned spending.
Key Points & Insights
β‘οΈ Project costs are internally funded by the organization; the customer payment (contract value) is a separate commercial discussion and does not alter the internal Project Cost or Budget.
β‘οΈ Contingency Reserve is for known risks and is part of the Project Manager's Cost Baseline; Management Reserve is for unknown risks and is outside the PM's direct purview.
β‘οΈ When determining costs, consider market conditions like Sole Source (single vendor, higher fee) versus Oligopoly (many vendors, higher negotiation control) for procuring specialized services.
πΈ Video summarized with SummaryTube.com on Nov 14, 2025, 19:51 UTC
Find relevant products on Amazon related to this video
As an Amazon Associate, we earn from qualifying purchases

Summarize youtube video with AI directly from any YouTube video page. Save Time.
Install our free Chrome extension. Get expert level summaries with one click.